送变电工程
Includes electric power transmission and transformation engineering in the electric power system ranging from transmission lines、 substations and supporting facilities and distribution lines
Project
City Grid reconstruction project of Huhehaote, Inner Mongolia Electricity Board
Constructing company
Huhehaote, Inner Mongolia Electricity Supply Co., Ltd
Equipping plan:
circuit route planning and put underground
Working range
primary drawings, working drawings and completing drawing designing
Period of project
2013
Project introduction
The project was finished in December 2013. 15-kilometer City Grid is designed. mainly involving 35kV and 10kV circuits and partial 110kV circuits, as an important project of city grid upgrade and reconstruction of Huhehaote Electricity Board